Building upon SG3’s success in helping SDOT improve performance on previous projects, we were engaged as the utility coordination lead for the design and construction of the $140M Lander Street Grade separation. Completed during the summer of 2020, this critical Move Seattle transportation improvement eases severe traffic congestion and improves public safety along a vital urban arterial. The new bridge elevates vehicle and pedestrian traffic over a multitrack rail crossing zone. A key challenge was that the bridge footprint lies runs parallel with and directly over a critical underground utility corridor with large-capacity sewer and storm water conveyance facilities.