Elliott Bay Seawall Project Diary


Scott Goss • Nov 23, 2013

FALL 2013


If You Like Slider Puzzles You'll Love This!

The design for the Elliott Bay Central Seawall Replacement is complete. Construction of the foundation for a new Alaskan Way and the re-imagined Seattle Waterfront is moving forward. Soon we get to where the rubber meets the road – literally!

The trick now is the slider puzzle of building all the components in the proper order, while dealing with all the external constraints – like parking, pedestrians, bicycles, permits, space, waterfront business needs, calendar restrictions, hours in the day – the list goes on! Significant portions of the utilities will be going through various levels of relocation and replacement. City crews will do some of the work while contractors will handle other items. Different trade contractors will be working side-by-side, in the same space.

While we have dealt with these elements and more so many times in the past, the combination of 1) the complexity of this project with 2) such a short construction schedule represents something of a “perfect storm” – and provides new challenges every day. We do get (and celebrate) the occasional piece of unexpected good news, such as the telephone provider telling us they have abandoned all their facilities within a whole section of our work area and it’s okay to tear through anything of theirs we happen to run into. Otherwise, this one is sort of a Utility Coordinator’s ultimate slider puzzle fantasy. So many prospects to boost value in the overall project equation (remember policy = implementation?) by thinking creatively and keeping the communication flowing!


SHARE

COMMENT

11 Dec, 2021
We're back...
By Scott Goss 01 May, 2017
Presented by Scott Goss, SG3 and Lorelei Williams, SDOT
By John Roth III 09 Mar, 2017
Spring 2017 – Elliott Bay Seawall Update
By Scott Goss, SG3 Strategies and Lorelei Williams, Seattle Dept of Transportation 05 Feb, 2017
Article
By John Roth III 13 Sep, 2016
From Health Hazard to Thriving Community
By John Roth III 13 Sep, 2015
Winter 2014/15 – Mass Excavation and CIP Slab Construction at the Elliott Bay Seawall
By John Roth III 03 Jul, 2015
Summer 2015 – Seattle's Historic Piers Reopen for Summer 2015
By John Roth III 27 Jun, 2015
Summer 2015 – Summer 2015 arrives at Seattle's Seawall project
By John Roth III 20 Jun, 2015
Summer 2015 – Final touches for Seattle Seawall construction at Waterfront Park
By John Roth III 01 May, 2015
Spring 2015 – Shelving for the Seattle Seawall habitat zone
More Posts
Share by: