Elliott Bay Seattle Seawall Project Diary


John Roth III • Mar 09, 2017

SPRING 2017


Elliott Bay Seawall Update

The Seawall Project team and Seattle Aquarium staff celebrating project completion in front of the aquarium.

This week marked a huge milestone on the Elliott Bay Seawall project. Work in front of the Seattle Aquarium finished THREE MONTHS ahead of schedule! SG3 is so pleased to have been part of this success, which required dedication, ingenuity, and teamwork from many talented team members.


To mark the occasion, the Seattle Aquarium removed the black paper that has covered their windows for nearly a year, and hosted a celebration at the facility’s Puget Sound Hall. They thanked the team for their terrific work on this three-year adventure, celebrating not only the Seawall completion, but also the team’s efforts to keep the Seattle Aquarium alive and thriving for all their guests.



We can’t wait to unveil the rest of the Seattle Waterfront’s transformation!


SHARE

COMMENT

11 Dec, 2021
We're back...
By Scott Goss 01 May, 2017
Presented by Scott Goss, SG3 and Lorelei Williams, SDOT
By Scott Goss, SG3 Strategies and Lorelei Williams, Seattle Dept of Transportation 05 Feb, 2017
Article
By John Roth III 13 Sep, 2016
From Health Hazard to Thriving Community
By John Roth III 13 Sep, 2015
Winter 2014/15 – Mass Excavation and CIP Slab Construction at the Elliott Bay Seawall
By John Roth III 03 Jul, 2015
Summer 2015 – Seattle's Historic Piers Reopen for Summer 2015
By John Roth III 27 Jun, 2015
Summer 2015 – Summer 2015 arrives at Seattle's Seawall project
By John Roth III 20 Jun, 2015
Summer 2015 – Final touches for Seattle Seawall construction at Waterfront Park
By John Roth III 01 May, 2015
Spring 2015 – Shelving for the Seattle Seawall habitat zone
By John Roth III 25 Mar, 2015
Spring 2015 – Closing the Seattle Seawall superstructure at Waterfront Park
More Posts
Share by: