Get in touch
555-555-5555
mymail@mailservice.com

Elliott Bay Seattle Seawall Project Diary


John Roth III • Jun 20, 2015

WINTER 2014/15


Final touches for Seattle Seawall construction at Waterfront Park

View north along Waterfront Park

laskan Way’s new form is taking shape at the north end of central seawall construction, along Waterfront Park. At the end of April the mass excavation trench still dominated the scene. Now, curb and gutter, sidewalks and other finished surfaces conceal the complex web of subsurface components. Paving is scheduled to begin June 23rd.


The end of June marks a transition point in the construction schedule, with the focus moving to the south end of the project through October 2015. Temporary pedestrian access will allow pier businesses to reopen for the summer tourist season.


Plenty of major utility restoration was completed in May. High voltage electrical duct banks were constructed.


View north – SCL duct bank installation

View north – SCL duct bank concrete poured

Water main and fire hydrants were installed.


View south – water main installation

Utility connections at the waterside of the seawall were required, with electrical services in protective cages.


Partially complete protective cage for electrical service at Pier 57

Then, time to backfill the big trench.

View north – backfill in progress

View north – backfill in progress

The land side temporary shoring wall was cut down.

View south – cutting the east shoring wall

Light-penetrating surface panels, sidewalk and surface finishes were installed.


New LPS and conventional sidewalks at Waterfront Park

View south at entry to Waterfront Park

North end of construction – waiting for final sidewalk segment

Here’s something of a cut-away view of the very north end of the finished wall construction, showing the various layers and components that make up the restored condition in the vicinity of Waterfront Park. This is the end of the season’s construction, so you see a bit of the transition to a temporary summer condition designed to maximize public access until construction resumes in October.


Looking west – north extent of construction

View south at north end of construction

SHARE

COMMENT

11 Dec, 2021
We're back...
By Scott Goss 01 May, 2017
Presented by Scott Goss, SG3 and Lorelei Williams, SDOT
By John Roth III 09 Mar, 2017
Spring 2017 – Elliott Bay Seawall Update
By Scott Goss, SG3 Strategies and Lorelei Williams, Seattle Dept of Transportation 05 Feb, 2017
Article
By John Roth III 13 Sep, 2016
From Health Hazard to Thriving Community
By John Roth III 13 Sep, 2015
Winter 2014/15 – Mass Excavation and CIP Slab Construction at the Elliott Bay Seawall
By John Roth III 03 Jul, 2015
Summer 2015 – Seattle's Historic Piers Reopen for Summer 2015
By John Roth III 27 Jun, 2015
Summer 2015 – Summer 2015 arrives at Seattle's Seawall project
By John Roth III 01 May, 2015
Spring 2015 – Shelving for the Seattle Seawall habitat zone
By John Roth III 25 Mar, 2015
Spring 2015 – Closing the Seattle Seawall superstructure at Waterfront Park
More Posts
Share by: