Get in touch
555-555-5555
mymail@mailservice.com

Elliott Bay Seattle Seawall Project Diary


John Roth III • Mar 25, 2015

SPRING 2015


Closing the Seattle Seawall superstructure at Waterfront Park

Looking north from vicinity of Pier 55

Construction activity continues at the Elliot Bay Seawall Project . The wall structure is nearing completion along Waterfront Park, while Improved Soil Mass jet-grouting continues at the south end of the current excavation zone.


This quick post provides a glimpse of current status and shows the final steps required for completing the assembly of the wall superstructure. With the Z-panel modules in place there’s still the need to tie everything together and close the wall. This is done with more steel and concrete.



Waterfront Seattle’s March 19th weekly progress update highlights this step. Our prior few posts show the wall installation sequence. Once complete, underground utilities are reinstalled and the excavation is backfilled. Then time to pave the new Alaskan Way.

Pedestrian level view from Waterfront Park, looking north.

North view closeup – closure wall partially complete along Waterfront Park

Z-panels tied together – back side of Z-panel vertical section

Z-panel heel section – reinforcing steel tie-downs

View south beyond south end of current excavation zone. Jet-grout rigs installing improved soil mass.

SHARE

COMMENT

11 Dec, 2021
We're back...
By Scott Goss 01 May, 2017
Presented by Scott Goss, SG3 and Lorelei Williams, SDOT
By John Roth III 09 Mar, 2017
Spring 2017 – Elliott Bay Seawall Update
By Scott Goss, SG3 Strategies and Lorelei Williams, Seattle Dept of Transportation 05 Feb, 2017
Article
By John Roth III 13 Sep, 2016
From Health Hazard to Thriving Community
By John Roth III 13 Sep, 2015
Winter 2014/15 – Mass Excavation and CIP Slab Construction at the Elliott Bay Seawall
By John Roth III 03 Jul, 2015
Summer 2015 – Seattle's Historic Piers Reopen for Summer 2015
By John Roth III 27 Jun, 2015
Summer 2015 – Summer 2015 arrives at Seattle's Seawall project
By John Roth III 20 Jun, 2015
Summer 2015 – Final touches for Seattle Seawall construction at Waterfront Park
By John Roth III 01 May, 2015
Spring 2015 – Shelving for the Seattle Seawall habitat zone
More Posts
Share by: